TWG
Hydro/Watershed Meeting Idaho Department of Water Resources
Monday, January
14, 2002
1:00 p.m.
Minutes
Introductions:
Dave
Hoover NRCS
Mike
Beaty USBR
Genna
Ashley-Poulson IDWR
Sandra
Thiel IDWR
Bart
Butterfield IDFG
Nathan
Bentley State GIS Coordinator
Tracy
Fuller - USGS
Al
Rea - USGS
Phone
Conference:
Douglas
Fitting Idaho Department of Lands, Coeur dAlene
Nick
Gerhardt Hydrologist, Nez Perce National Forest
Bill
Bogue EPA, Seattle
Leigh
Bailey - Boise, Payette National Forest
Sandy
showed the status map of USFS/USGS High Resolution NHD Production Project in
Idaho. Forest Service intends to do
all of Idaho, except for non-Forest land. Those
areas would include sub-basin numbers 17050103 (Middle Snake-Succor), 17050107
(Middle Owyhee), 17050108 (Jordan), and 17050115 (Middle Snake-Payette).
TWG needs to decide what to do with the remaining Hucs.
It would cost approximately $18,000 per Huc to process through a
contractor.
There
was a question on the table regarding following what Oregon/Washington did on
their hydro project. The concern
was that they are currently using a hybrid of two different systems (NHD, LLID)
and Idaho would like to stay with one system.
There
was an e-mail received from Brian Sanborn, (USFS NRIS Water) that had a July 1st
target date for completion of the southern and eastern border of the State.
All Salmon/Challis, Caribou, Targhee and Payette should be done by July 1st
also. Done would mean
linework done, built, etc., but the data could still be out for review and QC.
Tracy
Fuller remarked that if there is any federal money available, it would be a high
priority to earmark it for completion of the four remaining Hucs along the
border. USGS should know by June 1
about their funding levels.
Question
was raised about a contingent plan if no funding was available from USGS It
was decided that the TWG could contact Dan Wickwire (BLM) to see if there would
be any leftover money from BLM. The
group felt it would be counter-productive to get someone unfamiliar with the
process to finish the remaining hucs because of the time involved in the
learning process.
Tracy
Fuller suggested that, in the event of no funding or low-funding, the
appending/clipping process could be completed in-house, then the conflation
portion of the process could be given to the contractor at that point to save
some money.
It
was decided that it should be the responsibility of the TWG to apply for and
secure funding to finish the 24k hydrography portion of the 4 above-identified
hucs.
Mike
Beaty will add this request to his proposal and ask Oregon to support our
efforts. Mike meets with the Oregon
folks Thursday (1/17/02) in Portland.
Tracy
Fuller remarked that if funding could not be secured, it would mean more
in-house work for various agencies involved.
He also mentioned that only the 5th field is done along the
Humboldt (Nevada/Idaho border), primarily because there is not a lot of hydro in
that area, but this could possibly add four more partial hucs to our request.
Sandy
showed a list compiled of the primary landholders for each Huc (the top 10% in
most cases). She explained that
IDWR is currently in the process of reviewing the 5th/6th
level hucs for the state. IDWR
proposes that the TWG have an initial review with the primary landholders and
ask for people to look at the linework, then send back to the TWG with the
comments. Sandy also mentioned that
IDWR has a new ArcIms website with the review coverage available for download
for those who wish to review.
There
was a question on the table regarding whether or not to send out reviews to a
broad-based group or not. Dave
Hoover stated that we would not want to unintentionally exclude anyone from the
process and if was doubtful that anyone not directly involved with watersheds
would be interested in the review process anyway.
Nick
Gerhard suggested that the TWG identify a lead data steward for each huc based
on ownership acreage, and that other interested parties should be asked to
review hucs specific to their interest within each area.
Bill
Bogue mentioned that Dale Gunther with REO in Portland is setting up a
clearinghouse for Oregon Watershed data, and maybe Idaho could check into
getting some space on that site for review purposes.
Dave
Hoover brought up the question regarding how the actual changes were made for
that site, i.e., if the changes were made to that dataset, etc.
Bill Bogue said that it is a physical check-in/check-out site with edit
locks in place, with a data steward assigned.
This would be the system for a very detailed review process, and an
ArcIms site could be for casual reviews and checks.
Mike
Beaty remarked that a lead agency should be assigned as a data steward within
each huc and one person should be responsible for what happens within their
assigned huc.
Sandra
Thiel stated that the eventual goal is certification of all watersheds within
the state and it is a good idea to have a fairly detailed review process to
avoid the possibility of someone coming back later and saying they had no
opportunity for input, etc.
The
question was brought up regarding ownership acreage. If there are two agencies with very close acreages, would we
want both as data stewards or only one lead agency.
Nick
Gerhard suggested that it would be best to have only one lead agency per huc.
The agencies could get together and coordinate, but it would be better to
have one lead to avoid any confusion or duplicate datasets, etc.
Mike
Beaty remarked that in Washington they assigned each huc based on acreage, then
presented a request to the would-be data steward and gave them an opportunity to
either accept or decline the stewardship.
Nathan
Bentley agreed that this would be a good procedure so that the TWG knows who the
stewards are and to avoid someone getting stuck with the job.
This will hopefully avoid having someone commit to work and then not
doing it.
Leigh
Bailey stated that there was a map produced by Linda Davis some time ago showing
ownership by Forest Service (Region 1 and 4), BLM, IDWR, Boise Cascade and Idaho
Department of Lands. She also
thought it identified a main contact person from each agency.
Sandy
Thiel proposed using this resource, along with the Huc by Ownership
Acreage table. She will go
through the list and assign a primary steward for each huc and draft a letter
requesting they take the lead for that huc.
Part of the responsibilities will be to review the linework that exists
and not actually do any changes. They
would also coordinate the review process for their area.
Nick
Gerhard asked where the source data was for all watersheds
Sandra
Thiel explained that IDWR has data from a variety of different sources.
For example we have approximately nine coverages from the Panhandle, etc.
There are many contributors of data in both coverage and shapefile
formats and it would depend on the Huc in question as to the data source.
Leigh
Bailey asked if the data steward should receive comments on their hucs during
the review process or if it should be the responsibility of the TWG to get the
comments.
After
much discussion it was decided that if comments are taken from the steward, then
one place should be the data repository, and after the review period from the
steward the data would be returned back to the repository.
Lee stated that the dataset could then be returned to the TWG for the
actual changes, etc.
Sandra
Thiel proposed that after the data steward has reviewed the data, the TWG would
take the data, agree on the changes, and if necessary draw concept lines
in a group setting, then IDWR/NRCS, etc. would make the changes, and the Huc
would be sent out for further review to a broader-based group of interested
parties (possibly through an ArcIms site, etc.)
Nathan
Bentley agreed that the TWG would definitely want to review the proposed changes
made by the data stewards to ensure that they meet the FGDC National Standards,
etc.
Al
Rea stated that he is a member of the certification team (of about 10 people)
who will be reviewing hucs. They
will be looking at the big picture at this point from a national
prospective, and that all of the linework, and attributing must be completed.
Nick
Gerhard stated that if the data stewards submit changes, then the TWG should
encourage them to do the local coordination on their hucs before sending them
back to IDWR for physical changes.
Al
Rea explained that the concept lines could be drawn out 1st, at a
crude scale, then the work done for each huc.
Sandra
Thiel explained that Idaho would not need to do that in most cases, because the
lines have already been done, sometimes to the 10th level on some of
the data. The exception would be
changes regarding acreage limitations, etc.
Nick
Gerhard stated that he was the contact person for the Nez Perce National Forest,
Dick Jones was the contact for the Clearwater National Forest and Rick Patton
was the contact for the Panhandle National Forest and they could be contacts for
those areas.
After
some discussion it was decided that the process would be as follows:
1.
Potential
Data Stewards would be identified as per the Huc/Acreage list Sandy will
send out a letter requesting participation from each potential data steward.
2.
After
data stewards have accepted, hucs will be sent to them as they are completed by
IDWR (for linework, etc.), with a request for review and a time-frame that the
TWG would like to have them returned.
3.
The TWG
will meet again (round-table discussion) and discuss the proposed changes, agree
to make the proposed changes, etc.
4.
Agreed-upon
changes will be made by IDWR, or NRCS, etc., and then sent out to a
broader-based audience for review (possibly through the ArcIms site, etc.) with
a deadline for review and comments.
5.
After the
review period has expired, the TWG will meet again (this could possibly be done
through a NetMeeting) and again, review and make any additional changes, etc.
6.
The
Huc will then be ready for certification review.
A
question was raised as to who would have final say in the review process.
It was decided that, because the final goal is for certification in the
National Watershed Database, the TWG should take the responsibility of getting
the data ready for certification.
Sandra
Thiel agreed to make the list of potential data stewards and draft a letter
requesting stewardship. In cases
where the majority of the Huc acreage is private, the State would retain
stewardship.
It
was agreed that the linework would be done first to meet 24k standards before
sending out to data stewards.
Nick
Gerhard suggested that the group pick two or three hucs to run through a
pilot process to test the above procedure and make any necessary changes
before going any further. After
much discussion it was decided to put the following hucs through the review
process:
Huc 17010215 Panhandle National Forest
Huc 17040204 Wyoming Border Huc, Teton River
Huc 17050101 CJ Strike Dam
Al
Rea suggested a TWG meeting where a projector could be set up against a
whiteboard, together with all DRGs, etc., and everyone gets together makes
changes on the board, erases, etc., until the TWG agrees on changes to be made.
Those who could not participate could be present via NetMeeting, but may
not get the full benefit of the proposed changes due to the white board.
Nathan
Bentley stated that there could be a potential problem with Forest Service
people hooking up to a Net Meeting connection due to firewall restrictions, and
Al Rea suggested trying this out before the TWG meets next time.
After
some discussion, it was decided that the next TWG meeting would be Thursday,
February 28, 2002 in Conference Room C, IDWR at 1:00 p.m.
Action
Items:
1.
Sandra Thiel will identify potential data stewards based on ownership and
draft a letter requesting stewardship
2.
After data stewards are identified for Hucs 17010215, 17040204 and
17050101, they will be sent out for review.
3.
Connection will be tested for Net Meeting forest service hookups.
4.
Next Meeting 2/28/02 @ 1:00p.m. - IDWR
Meeting
Adjourned at approximately 3:15.